Project Management

Sprint deadlines are from the CMPUT 401 course calendar. Each sprint ends with a GitHub release at 20:00: Sprint 1 on September 29, Sprint 2 on October 13, Sprint 3 on October 27, Sprint 4 on November 17 (after reading week) and Sprint 5 on December 1, 2026. From Sprint 2, all work of a sprint is merged two days before its deadline (code freeze): October 11, October 25, November 15 and November 29. The release is made after the freeze. The client plans field testing in early December 2026.

Teamwork model

From Sprint 2, the team works in rotating full-stack mini-teams. Each mini-team also owns one technical area.

  • Full stack. Each mini-team does frontend and backend work.
  • One ownership area for each team. A team that owns an area makes sure that the area stays organised and that the other teams know about changes to it. The owner team does not do every task in that area.
  • One work area for each sprint. Each mini-team works on one main group of tasks in a sprint. The mini-teams assign their user stories themselves.
  • Offline sync meeting. One member of each mini-team goes to an offline meeting, so that all teams know about the changes and there are no knowledge silos.
  • Keep your team informed. If a member does not know what the team is doing, the other members of that team tell them about the work of (a) their mini-team and (b) the other teams.
  • Rotation. The teams and the ownership areas change after each sprint, so each member works in all three areas.

Ownership areas

Area What the owner team looks after
Platform / CI/CD / releases CI pipelines, PR checks, deployments, environments, migrations, release notes and rollback. The owner team makes all releases.
Architecture / backend / data The technical structure of the project: API conventions, database and schema changes, shared abstractions, large backend changes, refactors and dependencies. The owner team makes sure that the parts of the system stay consistent.
Quality / reliability / dev experience Unit, integration and E2E tests, logging, error handling, performance checks, security checks, linting and formatting, local setup, docs and debugging workflows.

Sprint 2 teams

These teams are for Sprint 2 only. The ownership areas were assigned at random.

Team Members Ownership area
Alpha Saumya, Aaron Architecture / backend / data
Beta Abhinav, Alissa Quality / reliability / dev experience
Gamma Zanab, Chris, Jayden Platform / CI/CD / releases

Sprint 3 teams

These teams are for Sprint 3 only. The ownership areas rotate, so that most members work in a new area. Only Chris (Platform) and Abhinav (Quality) keep their Sprint 2 area. Red owns Platform / CI/CD / releases and makes the Sprint 3 release. Red also has the map work, because the map, the GPX tracks and the offline layers are one connected piece of work. On October 24, five stories (24 points) moved from Sprint 4 to Sprint 3 and went to Red: 1.0.6, 2.0.12, 2.0.13, 3.0.3 and 3.0.4. On October 26, Frank required stewards to have an account and sign in. US 3.0.4 was removed and PR #310 was closed without merge. The current scope is 14 stories and 68 points.

Team Members Ownership area Points
Red Saumya, Chris Platform / CI/CD / releases 47
Blue Aaron, Zanab, Abhinav Quality / reliability / dev experience 15
Green Alissa, Jayden Architecture / backend / data 6

Story map

The full story set is in User Stories: 43 user stories in seven feature areas, 198 story points, prioritised with MoSCoW. The set follows the September 25, 2026 client meeting (see Meeting Minutes), plus later additions. Placement follows User Story Summaries.

Feature area Sprint 1 Sprint 2 Sprint 3 Sprint 4 Sprint 5 Unscheduled Won't Have
1 - People Management - 1.0.1 (5, M) ✓, 1.0.2 (3, M) ✓ 1.0.3 (2, S) ✓, 1.0.4 (2, M) ✓, 1.0.6 (2, S) ✓ 1.0.5 (5, C) - - -
2 - Place Management - 2.0.2 (3, M) ✓, 2.0.3 (3, S) ✓, 2.0.4 (8, M) ✓, 2.0.5 (5, M) ✓, 2.0.6 (5, S) ✓, 2.0.10 (1, M) ✓ 2.0.1 (8, S) ~, 2.0.8 (3, M) ✓, 2.0.9 (5, M) ✓, 2.0.12 (8, C) ✓, 2.0.13 (3, C) ✓, 2.0.14 (2, S) ✓ - - - 2.0.11 (5, W)
3 - Admin Persona - 3.0.2 (5, S) ✓ 3.0.3 (8, M) ✓ - - - 3.0.4 (3, W)
4 - General Features - 4.0.6 (1, M) ✓ 4.0.2 (13, S) ✓, 4.0.4 (5, S) ~ - - - 4.0.5 (5, W), 4.0.7 (5, W)
5 - Access and Accounts - 5.0.4 (2, S) ✓ 5.0.2 (2, M) ✓ 5.0.5 (8, M), 5.0.6 (5, M), 5.0.7 (8, M), 5.0.8 (5, M), 5.0.9 (3, M) - - -
6 - Data and Places - - 6.0.1 (5, M) ✓ - - - -
7 - Inspections and Media - 7.0.1 (2, C) ✓, 7.0.5 (5, S) ✓, 7.0.6 (5, S) ✓, 7.0.7 (5, M) ✓, 7.0.8 (5, S) ✓ - 7.0.3 (5, C) - - 7.0.4 (5, W), 7.0.9 (5, W)
Committed points 0 63 68 39 0 0 28

Numbers in brackets: story points and MoSCoW priority (M = Must Have, S = Should Have, C = Could Have, W = Won't Have).

✓ = done (merged on main, and the merged work covers each AT) as of the October 11, 2026 code freeze. All 16 Sprint 2 stories are done. See Sprint 2 status.

Sprint 3, as of October 26, 2026 (sprint-3 merged into main in PR #319): ✓ = merged, and the traceability matrix shows every AT covered. ~ = merged, but at least one AT is only partly covered or has no test (2.0.1 AT1 and 4.0.4 AT4). 12 stories (55 points) are ✓ and 2 stories (13 points) are ~. Updated October 27: 1.0.3 AT1 and 1.0.4 AT2 have labelled tests, so 1.0.3 and 1.0.4 moved to ✓. The code of 4.0.2 and 5.0.2 is ✓, but their production setup is not checked (see Sprint 3 release checks).

The Committed points row gives the story points of the stories placed in each sprint. The points that the team expects to finish in each sprint, from the Sprint 1 and Sprint 2 results, are in Velocity re-estimate. Sprint 4 has 7 stories (39 points) and one GitHub issue so far (#306, for 5.0.8). Sprint 4 is open on purpose (see Sprint 4). The client's new access-request stories use the capacity that the plan kept open in Sprint 4.

By MoSCoW:

Priority Stories Points Where
Must Have 19 85 8 in Sprint 2, 6 in Sprint 3, 5 in Sprint 4
Should Have 13 62 7 in Sprint 2, 6 in Sprint 3
Could Have 5 23 1 in Sprint 2, 2 in Sprint 3, 2 in Sprint 4
Won't Have 6 28 No sprint (2.0.11, 3.0.4, 4.0.5, 4.0.7, 7.0.4, 7.0.9)

Sprint 1 has no user stories because it is documentation and discovery. The team keeps Sprint 5 free on purpose: the client said that more work can come, and the sprint is also for final polish, deployment and field-test fixes.

Open conflicts with the plan. The Sprint 3 code freeze (October 25) was missed. sprint-3 merged into main on October 26 (PR #319). The tag and the open gates are in Sprint 3 release checks. 2.0.6 (map filter) was placed before the map (2.0.1, Sprint 3), and it is done in Sprint 2, so 2.0.1 builds on it, and 2.0.1 shipped in Sprint 3 on top of it.

  • Dependencies that still hold. 2.0.9 (GPX upload) shares Sprint 3 with 2.0.1 (map with tracks) and still comes first, because Frank asked for GPS files in one of the first sprints. 6.0.1 (site geometry) is in the same sprint as 2.0.1, which uses it. 2.0.13 builds on the priority points of 2.0.12, so the two stay together in Sprint 3.

MoSCoW is provisional. Frank has not confirmed the priorities yet. Issue #23 is closed, but its last comment says that no confirmation is recorded.

The ranked backlog of defects and tasks is in Issues Backlog.

Project plan

Scrum Master and Product Owner rotate each sprint. The full rotation is on the Teamwork page.

Team: Saumya, Chris, Zanab, Abhinav, Alissa, Aaron, Jayden

Scrum roles

The Scrum Master and the Product Owner change each sprint. The roles are described on the Teamwork page.

Sprint Scrum Master Product Owner
Sprint 1 Chris Alissa
Sprint 2 Aaron Chris
Sprint 3 Jayden Aaron
Sprint 4 Abhinav Zanab
Sprint 5 Alissa Abhinav

Sprint process

From Sprint 3, each sprint has its own branch, sprint-N (for example sprint-3), made from main. The GitHub ruleset allows branch names that start with sprint-.

  1. Each task is done on a feature branch. Its PR goes into sprint-N and needs 2 reviews.
  2. At the end of the sprint, one PR merges sprint-N into main. The Scrum Master of the sprint reviews it (Sprint 2: Aaron; Sprint 3: Jayden).
  3. Every sprint ends with a GitHub release built from main.

The steps are in Contributing. In Sprint 2, the PRs before #253 merged straight into main. The sprint-2 branch was made on October 11 at 9009d0d, the same commit as main. The later PRs (#253 to #262 and #276) merged into sprint-2. #284 merged sprint-2 into main on October 13 (squash commit ceb5188), and #285 merged main into release.

Milestones

All releases are GitHub releases at 20:00 on the due date.

Sprint Sprint goal Code freeze Release Stories Committed points
Sprint 1 Documentation and discovery: requirements, design, plan and teamwork - September 29, 2026 0 (documentation and discovery) 0
Sprint 2 Steward profiles, site administration, and SIR export and delete October 11, 2026 October 13, 2026 16 63
Sprint 3 Interactive map with site geometry, boundary colors and GPX tracks, inspection history, password reset, to-visit priority, export of all files and skill dropdowns October 25, 2026 October 27, 2026 14 68
Sprint 4 Activity points, the all-SIR summary and integrated access requests November 15, 2026 November 17, 2026 7 39
Sprint 5 New client requests, final polish, deployment and field-test fixes November 29, 2026 December 1, 2026 0 (not planned yet) 0

Velocity re-estimate

Update, October 26, 2026. Sprint 3 is measured in Re-estimate after Sprint 3. The text that follows is the October 11 and 12 record of the earlier plan.

Re-estimated on October 11, 2026, the Sprint 2 code freeze, from main at 9009d0d. A story counts as done only when its PR is merged on main and the merged work covers each AT of the story. During Sprint 3, Frank removed US 2.0.11, US 4.0.5 and US 4.0.7 from scope. Each has 5 points. They are now Won't Have (Won't Do), with no sprint. The scope totals fell from 60 to 45 committed points and from 57 to 42 re-estimated points. US 2.0.14 then moved from Sprint 4 to Sprint 3, which brings the Sprint 3 commitment to 47 points. The recorded re-estimate stays at 42 points. The velocity-based capacity remains 57 points. On October 24, five Sprint 4 stories (1.0.6, 2.0.12, 2.0.13, 3.0.3 and 3.0.4, 24 points) moved to Sprint 3. At that date Sprint 3 had 71 points and Sprint 4 had 39 points. The recorded Sprint 3 re-estimate stays at 42 points. On October 26, US 3.0.4 was removed (3 points), so the current Sprint 3 scope is 68 points.

Formula.

  • Done points = the sum of the story points of the stories that are Done.
  • Velocity per person per week = Done points / number of members / weeks in the sprint.
  • Re-estimate of a sprint = velocity per person per week × members × working weeks in the sprint.

Measured velocity. The team has 7 members in each sprint.

Sprint Committed Done Done per person Notes
Sprint 1 0 0 0 Documentation and discovery. No stories.
Sprint 2 63 63 9.0 51 points (7.3 per person) were done on October 9. The last 12 points (2.0.6, 5.0.4 and 7.0.6) were done on October 10 and 11.
Sprint 3 68 55 (68 merged) 7.9 (9.7 merged) As of October 27, 2026. All 14 stories are merged on sprint-3. Done counts only the stories whose ATs are all covered; 2.0.1 and 4.0.4 (13 points) have a partly covered AT. US 3.0.4 (3 points) was removed on October 26 and is not counted.

Sprint 2 by team. A team's points are the points of the stories that the plan gave to it. Some PRs were written by members of another team: 2.0.3 by Jayden (PR #150), 7.0.5 by Chris (PR #148), and the last ATs of 2.0.6, 5.0.4 and 7.0.6 by Saumya (PR #241, PR #238, PR #237).

Team Members Committed Done on October 9 Done on October 11 Per person (October 11)
Alpha 2 15 13 15 7.5
Beta 2 19 14 19 9.5
Gamma 3 29 24 29 9.7
Total 7 63 51 63 9.0

Re-estimate. Revised on October 12 for the length of each sprint (#266). Sprint 2 was 2 weeks long and had 7 members, so it gives two measures per person per week:

Measure Arithmetic Points per person per week
Done on October 9, before the freeze-week fixes 51 / 7 / 2 3.6
Done at the freeze, October 11 63 / 7 / 2 4.5
Planning rate (midpoint of 51 and 63 = 57 points) 57 / 7 / 2 4.07

The re-estimate uses the planning rate. The reasons:

  • The first week of Sprint 2 went to setup: four dev tasks with no story points (branch model, admin auth checks, the Invalid Identifier fix and the W26_ rename) and the two user model tasks of 1.0.1. Sprint 3 has no setup work, so the team can do more than 7.3.
  • The last 12 points of Sprint 2 needed fix PRs on October 10 and 11 from one member. The team cannot plan on that again, so it does not use 4.5.

Re-estimate of a sprint = 4.07 × 7 members × working weeks. Sprint 4 runs for 3 calendar weeks, but one of them is reading week, and the plan counts no story work in reading week.

Sprint Dates Working weeks Arithmetic Re-estimate Committed Difference Plan
Sprint 3 Oct 14 to Oct 27 2 57 − 15 (scope change) 42 68 26 over Three stories removed; US 2.0.14 and five Sprint 4 stories added. US 3.0.4 removed on October 26. Capacity remains 57.
Sprint 4 Oct 28 to Nov 17 2 (3 weeks minus reading week) 4.07 × 7 × 2 57 39 18 free Room for Sprint 3 carry-over.
Sprint 5 Nov 18 to Dec 1 2 4.07 × 7 × 2 57 0 57 free 30 points for new client stories. The other 27 are for deployment, final polish and fixes from the December field test.

If the team also works in reading week, Sprint 4 can take 4.07 × 7 × 3 = 85 points. The plan does not count on it.

Re-estimate after Sprint 3

Made on October 26, 2026, from sprint-3 at the merge of PR #319. The formula is the same as above. Sprint 3 was 2 weeks long and had 7 members.

Measure Arithmetic Points per person per week
Merged 68 / 7 / 2 4.86
Done, every AT covered 55 / 7 / 2 3.93
Planning rate (midpoint of 55 and 68 = 61.5 points) 61.5 / 7 / 2 4.39

The planning rate is a little above the Sprint 2 rate of 4.07. The midpoint is used for the same reason as in Sprint 2: the merged figure includes two stories that still have a partly covered AT. The load was also uneven. Saumya and Chris made 87 of the 124 non-merge commits since October 14 (see Teamwork), so the team cannot plan on the 68 as an even rate.

Sprint Dates Working weeks Arithmetic Re-estimate Committed Difference Plan
Sprint 4 Oct 28 to Nov 17 2 (3 weeks minus reading week) 4.39 × 7 × 2 61 39 22 free Room for the Sprint 3 gaps (13 points of stories with a partly covered AT, mostly tests) and for new access-request work.
Sprint 5 Nov 18 to Dec 1 2 4.39 × 7 × 2 61 0 61 free 30 points for new client stories. The other 31 are for deployment, final polish and fixes from the December field test.

Sprint 4 and Sprint 5 are 4 points higher than the October 12 estimate of 57. The Sprint 4 Product Owner (Zanab) should spread the load across the three teams. Sprint 3 gave Red 47 of 68 points.

Sprint 3 scope change. The three removed stories are not carry-over to Sprint 4. Their tasks are excluded from the current plan. US 3.0.4 was also removed on October 26; it is not carry-over.

Sprint 3 risk. Sprint 3 needs 68 / 7 = 9.7 points per person. This is above the 9.0 of Sprint 2 on October 11 and the 7.3 of October 9. The load is not even:

Team Members Points Per person
Red 2 47 (1.0.6: 2, 2.0.1: 8, 2.0.9: 5, 2.0.12: 8, 2.0.13: 3, 3.0.3: 8, 4.0.2: 13) 23.5
Blue 3 15 5.0
Green 2 6 3.0

Red has 23.5 points per person, which is 2.4 times the highest team result of Sprint 2 (Gamma, 9.7). 4.0.2 alone is 13 points. The four moved stories that remain add 21 points to Red, so the offline layer tasks of 4.0.2 are the first work to move back.

Mitigation (proposed for the October 14 planning; the Product Owner decides).

  • If Red has not merged the map page (#184) and the GPX track table (#185), both due October 17, by October 20: the offline layer tasks of 4.0.2 (#207, #209, #213) move to Sprint 4. This move would raise Sprint 4 from 39 to 52 points, which is within the capacity of 57. Blue (5.0 points per person) takes the GPX upload tasks of 2.0.9 (#192, #201).
  • If the offline work moves, Sprint 3 has 55 points and Sprint 4 has 52 points. The Product Owner must review the load.

The base map, the protected area boundaries, the map filters and the map search (PR #159, PR #161, PR #166, PR #167, PR #241) are already on main. 2.0.1 builds on them. No Sprint 2 work carries over into Sprint 3.

Sprint 1

Due: September 29, 2026, 20:00 (GitHub release).

Sprint 1 is documentation and discovery. There is an existing codebase inherited from two previous teams, so a large part of this sprint is establishing what actually exists before committing to a backlog.

Tasks

Task Related US Assignee Due
User Stories Documentation Alissa, Saumya Sep 26th
Project Requirements Doc Documentation Alissa Sep 26th
Project Overview: exec summary, glossary, similar products Documentation Zanab Sep 26th
UML Class and Sequence Diagrams Documentation Jayden Sep 26th
High-Level Architecture Diagram Documentation Saumya Sep 26th
Low-Fidelity Wireframes and UI Flow Diagram Documentation Abhinav Sep 27th
Software Design Doc Documentation Abhinav Sep 27th
Project Management Doc Documentation Saumya Sep 28th
Team Canvas Documentation Everyone Sep 19th (done)
Teamwork Doc Documentation Chris Sep 19th (done)
Handover investigation of inherited codebase Documentation Saumya Sep 21st (done)
Issues backlog and prioritisation Documentation Saumya Sep 21st (done)
Meeting minutes for Fall 2026 to date Documentation Chris Sep 26th
UI audit of the deployed application Documentation Aaron Sep 22nd (done)
Mobile application user stories Documentation Chris Sep 27th (dropped, not needed)
Confirm scope and open questions with client Documentation Saumya, Alissa Sep 26th

Sprint 2

Due: October 13, 2026, 20:00 (GitHub release). Code freeze October 11.

All Sprint 2 work is finished and merged by October 11 (code freeze), two days before the deadline. Gamma makes the release on October 12. October 13 is spare time before the 20:00 deadline. Tasks are assigned to teams, not to people. The teams were chosen at random: each team got a share of the work in proportion to its number of members, and the tasks in its ownership area. Each team divides its tasks between its members.

Teams: Alpha (Saumya, Aaron), Beta (Abhinav, Alissa), Gamma (Zanab, Chris, Jayden). See Teamwork model.

Scrum roles: Scrum Master Aaron, Product Owner Chris. See Scrum roles.

The security stories were removed from the story list on September 25, so the access control work stays in the task list below until the team decides if it returns as stories.

Sprint 2 release (October 13, 2026)

  • Merges. PRs #253 to #262 and #276 merged into sprint-2. #284 merged sprint-2 into main on October 13 (squash commit ceb5188). #285 merged main into release. The branches chore/sprint-2-integration, sprint-2 and test/fix-test-case-error no longer exist.
  • Release. The GitHub release sprint-2 was published on October 13. The release notes issue (#97) and the code freeze issue (#96) are closed.
  • Checks. GitHub Actions cannot run, because the organisation's billing failed, so #284 and #285 were merged with an admin bypass. The CI job list was run locally on main at ceb5188 and passed: tsc --noEmit, npm run test:ci (111 suites, 1524 tests passed, 5 skipped, 0 failed), npm run build, ESLint with --max-warnings 0, .githooks/test-hooks.sh, npm run diagrams:check and mkdocs build --clean.
  • Follow-ups. The Sprint 2 rubric follow-ups (#263, #265 to #270 and #272 to #274) are closed. Each was done by a PR that merged into ci/lint-clean-and-blocking and reached main through #262 and #284; see the table under Other issues in the Sprint 2 milestone. No Sprint 2 work carried over to Sprint 3. The only open Sprint 2 issue is the demo, review and retrospective (#98).

Sprint 2 status (as of October 11, 2026)

This status was read from main at 9009d0d on October 11, the code freeze. The release was made on October 13, see Sprint 2 release. A story or task is Done when its PR is merged on main and the merged work covers each AT of the story. The test of each AT is in the Traceability Matrix. A gap in the tests of a Done story is listed below the table. It does not change the status.

Tests. A full local Jest run on 9009d0d passes: 103 suites and 1367 tests. CI did not run on the commits from e39cc8f (PR #243) to 9009d0d, because GitHub did not start the jobs: the account's Actions payments failed. The last CI run that ran the tests was on 2cf69c6 on October 10 (96 suites, 1235 tests, all passed). CI has not run since. The local checks of the release are under Sprint 2 release.

Sprint 2 fixes after the freeze. The fixes of Alpha, Beta and Gamma, the caller checks on the report read actions (#251, fixed by PR #259) and the CI changes were merged into sprint-2 as PRs #253 to #262 and #276. They change no story status. They are on main since #284. On main at ceb5188, local runs give tsc 0 errors, ESLint 0 problems, npm run build passing, and npm run test:ci 111 suites passed (1 skipped) and 1524 tests passed (5 skipped, 0 failed), with coverage of statements 85.06%, branches 74%, functions 78.61% and lines 87.56%. These are local results: GitHub Actions has not run since October 10.

Quality gates on main (Contributing): lint fails the webapp-tests job on any problem (--max-warnings 0), npm run test:ci fails below the coverage thresholds in webapp/jest.config.ts, e2e.yaml runs seven Cypress specs against a local Supabase on PRs into main and release, and the PR checks, the reviewer gate and the diagrams workflow also run on PRs into sprint-*.

Status Stories Points
Done 1.0.1, 1.0.2, 2.0.2, 2.0.3, 2.0.4, 2.0.5, 2.0.6, 2.0.10, 3.0.2, 4.0.6, 5.0.4, 7.0.1, 7.0.5, 7.0.6, 7.0.7, 7.0.8 63
Partial - 0
Not started - 0
Total 16 stories 63
  • Done. 63 of the 63 committed points (16 of 16 stories), up from 51 on October 9 and 30 on October 7. The last three stories were finished on October 10 and 11:
    • 2.0.6 AT3: the map search lists the matching protected areas, and picking one centres the map on it with fitBounds (PR #241, October 10). Tests: SiteMap.test.tsx:442,455 and Sites.test.tsx:775.
    • 5.0.4 AT3: the terms page has the user menu with Logout (PR #238, October 11). /api-docs is the Swagger reference for developers. It is exempt, as the comment in webapp/app/api-docs/page.tsx says. All other signed-in pages have a sign-out control.
    • 7.0.6: the 50-site cap was removed before Fall 2026, in commit dde6ccb (July 22, 2026, by the Winter 2026 team). PR #237 (October 10) makes the export read past the PostgREST limit of 1000 rows and adds tests for AT1 (a 60-report and a 51-report export, a 60-site request), AT4 (a failed export of 51 reports writes only to the job table) and paging. AT3 was already tested. PR #258 adds AT2 (51 reports have the same answers in the export as on the site page) and a 60-report steward refusal for AT3.
  • Work merged on October 10 and 11 (PR #234 to PR #250). Besides the three stories above:
    • CI runs the build, the type check and lint (PR #235). At the freeze, lint reported its errors on main but did not fail the job. PR #262 makes lint blocking and PR #260 adds the coverage gate (see Quality gates above).
    • Fixes: gallery reads and a safe image delete (PR #234), drafts that restore reliably (PR #236, #87), profile save errors, approved-only reads and steward search (PR #238), archived and inactive sites (PR #239), auth gaps in the middleware, the OAuth callback and the admin layout (PR #240), caller checks on the report write actions (PR #242) and a test mock (PR #249).
    • Tests labelled with their stories and the AT gaps filled (PR #243).
    • Docs: meeting minutes and contributions (PR #244), interfaces and design decisions (PR #245), the release process and the production migration runbook (PR #246), diagrams (PR #247), this status (PR #248) and the October 9 client slides (PR #250).
    • Manual steps in production: PR #234 and PR #238 each add a migration that a person runs in production. PR #240 asks for the passwords of the three Cypress test accounts to be rotated. See Production database migrations.
  • Test gaps in Done stories. On main at 9009d0d, one AT had no test (2.0.2 AT5) and 15 were tested only in part. The fixes after the freeze add tests for 2.0.2 AT5, 2.0.5 AT1, AT2 and AT4, 2.0.6 AT2 and 7.0.6 AT2. On main at ceb5188 every AT has a test, and 5 ATs are tested only in part (2.0.3 AT4, 2.0.4 AT3, 7.0.1 AT3, 7.0.5 AT1 and AT3), for example 7.0.5 AT1: no test renders a report after an image delete. The list is in the coverage summary.
  • Known limit of 2.0.6. The map draws protected areas. PR #167 links a site to its area with a new column that the migration does not fill. A site shows on the map only when an Admin links it. Sprint 3 task #181 fills the link from the KML.
  • Still open. The code freeze issue (#96) and the release issue (#97) are closed. The demo, review and retrospective (#98, October 14) are ahead.

Issue state does not match the evidence. This list is a report only. The owner team corrects its issues.

Sprint 1 TA feedback and revisions

The rows below are the TA's advice in the September 23 lab (see Meeting Minutes, Meeting #3) and in the week 5 lab notes of September 30 (docs/meetings/week5/Meeting_Notes.md, Meeting #6). Each row shows what the team did with the advice. Done means the change is on main or in the docs. Partial means that part of the advice is not applied yet, and the row names the plan for the rest. Planned means that the work has an owner and a date and has not happened yet. Deferred means that the work moves to a later sprint, for the reason given. Decided means that the team chose not to follow the advice, for the reason given. Not verifiable means that no source records whether the team followed the advice. The TA (Alex) is CC'd on all client emails, so he sees the client's answers directly.

TA point Date Action taken Evidence Status
Remove "As a Developer" stories. Sep 23 The story set has no developer stories. DevOps and release work is in the task tables as Dev Task rows. The September 19 question to the TA, whether DevOps work can be a story, has no answer in the minutes. User Stories; task tables below Done
Merge small stories and think at a higher level. Sep 23 Stories are grouped into seven feature areas and tied to charter projects. Two 1-point stories stay separate (2.0.10 and 4.0.6): each is its own item in charter project 1. Story map; User Stories Decided: 2.0.10 and 4.0.6 stay separate, because each is its own charter item. Both are done.
Write stories that touch Frank's pain points, well developed and exciting, not general. Sep 23 The team presented its stories to Frank on September 25. Frank asked for each story to be mapped to the charter projects on the SAPAA website. Each of the 40 stories now names its charter project. User Stories; Meeting Minutes (September 25) Done
Frank may want geobounds for sites on a map. Sep 23 An Admin picks the boundary of a new site from the Alberta government KML (PR #153, PR #162), and the map draws the protected area boundaries (PR #161). Linking each existing site to its boundary is US 6.0.1 in Sprint 3. 2.0.2 AT1 and AT6; #181 Done. US 6.0.1 is merged (PR #294, PR #303, PR #313) and #181 is closed. The link runs when an Admin imports a KML.
Pitch the mobile app as a PWA, and check offline use (Android supports offline PWAs, iOS needs a check). Sep 23 Not pitched. On September 25 Frank said that he needs offline capability on the web app, and that offline is not in a charter project. The team planned offline map layers for the web app (US 4.0.2, Sprint 3) and no PWA story. Meeting Minutes (September 25); US 4.0.2 Decided: offline is built as web map layers, because Frank asked for offline on the web app
Until Friday (September 25), write nothing new. Sep 23 Meeting #3 records the advice, but no source records whether the team stopped other writing until September 25. Meeting #4 does not mention it, and the git history cannot show what was written outside the repository. - Not verifiable: nothing recorded whether other writing stopped
The Sprint 1 deadline is Tuesday evening and must be a GitHub release. Sep 23 The GitHub release "Sprint 1 Release" (tag sprint-1) was published on September 29 at 17:15 MDT. Each later sprint also ends with a GitHub release built from main. Sprint process Done
Use the GitHub project board for the filtered issues. Sep 23 Sprint 2 stories and tasks are issues in the Sprint 2 milestone, on the SAPAA project board (for example #54). The Sprint 3 issues are on the board too (for example #169). Sprint 2 Done
Prepare a presentation of about 15 minutes with the most interesting stories, and present it to Frank on Friday. Sep 23 The team presented its stories and plan to Frank on September 25. (This row merges two rows that both recorded this presentation.) Meeting Minutes (September 25) Done
In standups, teammates should know what the others are doing. Sep 23 The teamwork model has an offline sync meeting and a rule to keep the team informed. The Sep 23 minutes record that the TA (Alex) will run an exercise where each member describes another member's work. They do not record that it took place. Plan: at the October 14 lab, Aaron (Sprint 2 Scrum Master) asks Alex to run the exercise, and the minute-taker records it in Meeting #10. Teamwork model; Meeting Minutes (Meeting #10) Not verifiable: Meeting Minutes has no minutes of the October 14 lab, so no source records whether the exercise took place. Issue #264 is closed, but the minutes are not in the file.
Ask Frank which behaviours the gamification should reward, and find metrics for them. Pitch a bounty board that gives more points for chosen sites. Sep 23, Sep 30 On October 9 the team showed Frank a gamification mock-up: top contributor, counties visited, variety of site types and subtypes, natural regions, a time dimension and the first reporter of a site. Frank said the direction is right. The bounty board is deferred. It was not raised with Frank on October 2 or October 9. On October 2 Frank asked for simple gamification built from data that already exists (Meeting #7). On October 9, about the mock-up metrics, he said: "use the data that you have". A bounty board needs new data, a points value for each chosen site, which is the to-visit priority of 2.0.12 in Sprint 4. Plan: Aaron (Sprint 3 Product Owner) asks Frank at the October 16 client meeting whether the 2.0.12 priority should give more activity points (1.0.5), and records the answer in the minutes. docs/meetings/week6/2026_10_09_meeting_frank.txt; US 1.0.4 (Sprint 3), US 1.0.5 and US 2.0.12 (Sprint 4) Partial. Bounty board deferred to Sprint 4 (2.0.12, 1.0.5); question to Frank on October 16, owner Aaron
Do not delete site data. Mark the site as deleted and hide it. Sep 30 A site can be archived (hidden, and it can be restored). An archived site can also be deleted for good. Frank asked for both levels on October 2 and approved them on October 9. PR #160; docs/meetings/week5/2026_10_02 _meeting_Frank.txt; docs/meetings/week6/2026_10_09_meeting_frank.txt Done
Generate the UML from the code base. Sep 30 A diagram generator builds the diagrams from the migrations and the TypeScript, and updates them on every PR into main, release or sprint-*. A check that fails when a diagram is out of date exists: npm run diagrams:check (node tools/diagrams/src/cli.mjs check). The workflow diagram-svg-check.yaml runs the diagram tests and check --svg-only on every PR into main, release or sprint-*. It checks source and SVG hashes from the last successful render (Sprint 3 task #196). PR #157; Contributing Done. Merged in PR #305; diagram-svg-check passes on PR #319. Task #196 is closed.
Build the map in layers: a static layer of polygons from Alberta open data, a dynamic layer of GPX tracks, and a data layer. Sep 30 The team chose OpenStreetMap data because Google Maps does not allow caching tiles offline. This reason is the team's own research: the Sep 30 notes record it, but do not say who raised it. The base map uses MapLibre GL with a Protomaps basemap (OpenStreetMap data). The protected area boundaries are imported and drawn. The GPX track layer is planned for Sprint 3 (2.0.9 and 2.0.1). No story covers the data layer yet. It was a Sprint 4 candidate. Sprint 4 now has 39 points and 20 free (see Re-estimate after Sprint 3). No source records which data Frank wants this layer to show. Plan: Aaron (Sprint 3 Product Owner) asks Frank which data the layer shows at the October 16 client meeting. Zanab (Sprint 4 Product Owner) brings it to Sprint 4 planning (October 28 lab), where adding it requires other work to move out. PR #159; PR #137; PR #152; PR #161; PR #167 Partial. Data layer: no story yet. The October 16 and October 23 minutes do not record the question to Frank (Aaron). Zanab brings it to Sprint 4 planning (October 28 lab).
Ambiguity in a story should not change its points. A story is not complete until its details are clear. Sep 30 The plan lists unclear stories as open conflicts and marks MoSCoW as provisional (issue #23). No change was made in Sprint 2: the points of the Sprint 2 stories are the same as in the Sprint 1 release (tag sprint-1, September 29), which came before this advice. The Sprint 3 plan now has an "open questions before pointing" step, owned by Aaron (Sprint 3 Product Owner) from the October 14 planning. Open questions before pointing Partial: the Sprint 3 section has the step. No minutes of the October 14 planning record that Aaron ran it.

Sprint 2 TA feedback and revisions

The TA gave three points after Sprint 2: too many PRs got only an "LGTM" review, too many branches were made for small documentation changes, and too much GitHub Actions time was used. The statuses use the words of the Sprint 1 table above. The counts come from gh pr list, gh pr view and gh run list on October 26, 2026.

TA point Action taken Evidence Status
Too many PRs only got "LGTM" reviews. Some Sprint 3 reviews name what they checked: #321 against #183, #309 (a security change request, then a fix) and #305. Short reviews remain: of the 28 PRs merged into sprint-3, 14 have only empty or one-line approvals (under 45 characters) and 3 have no human review (#287, #293, #299). Copilot "unable to review" comments are not counted as reviews. Proposed rule for Sprint 4: a review of a story PR lists the ATs it checked, and the Scrum Master checks this. PR #309, PR #321, PR #305 Partial
Too many branches for small docs changes. The branch model is main, sprint-3, then one branch per story. No Sprint 3 branch name has a team name. 30 PRs targeted sprint-3 (28 merged, 2 closed) for 14 stories, about 2 per story. Before Sprint 3, 125 PRs targeted main (96 merged, 29 closed without merge), including 15 closed PRs from alpha branches (#219 to #233). Docs-only PRs merged into sprint-3 are #302, #314 and #317. #304 was closed as a duplicate of #314. From now on, small docs changes are commits on sprint-3. Contributing Partial
Too much GitHub Actions time. Workflows moved to the self-hosted runner in PR #316, and the E2E job does not run on PRs into sprint-*. The last 100 runs (about 2 hours on October 26) show 46 cancelled, 36 successful, 16 failed and 2 skipped; 76 were started by PRs. Re-runs after pushes still cancel many runs. Push a set of commits together instead of each commit. Contributing Partial

User stories

User Story Story points Status
US 1.0.1 - Add User Profiles 5 Done (#54; PR #131, PR #138, PR #141, PR #142)
US 1.0.2 - Allow Editing Own Profile 3 Done (#55; PR #138, PR #151)
US 2.0.2 - Allow Admins to Add New Sites 3 Done (#56; PR #153, PR #162, PR #167)
US 2.0.3 - Deactivate and Reactivate a Site 3 Done (#57; PR #150)
US 2.0.4 - Delete a Site 8 Done (#58; PR #160)
US 2.0.5 - Update a Site 5 Done (#59; PR #163)
US 2.0.6 - Search and Filter Sites by County on the Map 5 Done (#60; PR #159, PR #161, PR #166, PR #167; data in PR #132, PR #137, PR #152; AT3 in PR #241)
US 2.0.10 - Add links to Site Page 1 Done (#61; PR #145)
US 3.0.2 - Steward Designation 5 Done (#62; PR #133, PR #139, PR #140)
US 4.0.6 - Demote Photo Identifier to optional field 1 Done (#63; PR #147)
US 5.0.4 - Sign Out Properly 2 Done (#64; PR #120, PR #158, PR #238)
US 7.0.1 - Let Stewards Export Their Own Reports 2 Done (#68; PR #155)
US 7.0.5 - Delete an Image and Clean Up After It 5 Done (#65; PR #148)
US 7.0.6 - Export More Than 50 Site Inspection Reports 5 Done (#66; cap removed in dde6ccb before Fall 2026; paging and tests in PR #237)
US 7.0.7 - Hide Fields on a SIR Before Export 5 Done (#67; PR #146)
US 7.0.8 - Delete a Site Inspection Report 5 Done (#69; PR #165)

Committed: 63 points. Done: 63 points (October 11).

Tasks

Task Related US Assignee Due Status
Set up development, release, and feature branches (issue title: "Set up prod branch") Dev Task Gamma (Zanab, Chris, Jayden) Oct 4th Done (#70; PR #125)
Improve authentication checks for admin routes Dev Task Beta (Abhinav, Alissa) Oct 4th Done (#71; PR #144)
Investigate and fix Invalid Identifier Supabase error Dev Task Alpha (Saumya, Aaron) Oct 4th Done (#72; PR #128)
Update db names to not include "W26" as prefix Dev Task Alpha (Saumya, Aaron) Oct 4th Done (#73; PR #129)
Create user model that supports profiles, steward assignments, and gamified stats US 1.0.1 Alpha (Saumya, Aaron) Oct 4th Done (#74; PR #116, PR #130)
Migrate user model US 1.0.1 Alpha (Saumya, Aaron) Oct 5th Done (#75; PR #131)
Profile page US 1.0.1 Alpha (Saumya, Aaron) Oct 6th Done (#76; PR #138, PR #141, PR #142)
Add Steward to site page and link to their profile US 3.0.2 Alpha (Saumya, Aaron) Oct 7th Done (#77; PR #133, PR #139, PR #140)
Edit profile/user info page and functionality US 1.0.2 Alpha (Saumya, Aaron) Oct 7th Done (#78; PR #138, PR #151)
Add new site page and functionality US 2.0.2 Gamma (Zanab, Chris, Jayden) Oct 5th Done (#79; PR #153, PR #162, PR #167)
Edit existing site page fields US 2.0.5 Gamma (Zanab, Chris, Jayden) Oct 6th Done (#80; PR #163)
Delete site button and confirmation US 2.0.4 Gamma (Zanab, Chris, Jayden) Oct 6th Done (#81; PR #160)
Deactivate/Activate button and confirmation US 2.0.3 Beta (Abhinav, Alissa) Oct 6th Done (#82; PR #150)
Set up map US 2.0.6 Beta (Abhinav, Alissa) Oct 7th Done (#83; PR #159)
Add sites to the map US 2.0.6 Beta (Abhinav, Alissa) Oct 6th Done (#84; PR #161, PR #167; draws protected area boundaries, and a site shows only when linked to an area)
Add Search and Filtering on Map view US 2.0.6 Beta (Abhinav, Alissa) Oct 7th Done (#85; PR #166, PR #167, PR #241)
Add links to site page US 2.0.10 Gamma (Zanab, Chris, Jayden) Oct 7th Done (#86; PR #145)
Fix site inspection page resetting current page when app is exited temporarily US 4.0.6 Beta (Abhinav, Alissa) Oct 6th Done (#87; PR #164)
Change Photo Identifier field on SIR to not required US 4.0.6 Beta (Abhinav, Alissa) Oct 5th Done (#88; PR #147)
Add a delete option on images US 7.0.5 Beta (Abhinav, Alissa) Oct 7th Done (#89; PR #148)
Increase export limit to over 50 US 7.0.6 Gamma (Zanab, Chris, Jayden) Oct 9th Done (#90; dde6ccb, PR #237)
Screen to select hidden fields on SIR before export US 7.0.7 Beta (Abhinav, Alissa) Oct 9th Done (#91; PR #146)
Grant Steward permission to export PDFs US 7.0.1 Gamma (Zanab, Chris, Jayden) Oct 7th Done (#92; PR #155)
Delete site inspection report button and confirmation US 7.0.8 Gamma (Zanab, Chris, Jayden) Oct 7th Done (#93; PR #165)
Fix logging out functionality outside the home page US 5.0.4 Alpha (Saumya, Aaron) Oct 5th Done (#94; PR #120, PR #158, PR #238)
Open a PR for each task and request 2 reviews All US Everyone Oct 10th Done (#95, closed on September 29, before the work started. Each story and task has a merged PR)
Code freeze: all Sprint 2 PRs reviewed and merged All US Everyone Oct 11th Done on main at 9009d0d; the issue is closed (#96)
Write the release notes and make the Sprint 2 release on GitHub Release Gamma (Zanab, Chris, Jayden) Oct 12th Done (#97 is closed; #284, #285 and the sprint-2 release, published on October 13)
Sprint 2 demo, review and retrospective All US Everyone Oct 14th Not started (#98)

Other issues in the Sprint 2 milestone

The Sprint 2 milestone has 16 more issues. They are not in the task table because they are not Sprint 2 stories or tasks: one is a removed story, four are Sprint 1 documentation checks that were moved to Sprint 2, one (#252) tracks the fixes from the Sprint 2 rubric review, and 10 (#263, #265 to #270 and #272 to #274) are the Sprint 2 rubric follow-ups. All 16 are closed. Issue #264 (minute the October 14 lab) is in the Sprint 3 milestone, because it is future work.

Issue Title State Why it is not a Sprint 2 task
#5 US 3.0.8 - Separate app access from admin access Closed as not planned (September 29) The security stories were removed on September 25. The work continued in task #71 and in PR #240 (the approval gate in the middleware).
#18 Belbin roles contradict themselves in three places Closed (September 29, PR #99) Sprint 1 documentation. Teamwork now builds the role lists from the table.
#19 Add the September 19 transcript to the repo Closed (October 9), no closing note Sprint 1 documentation. The transcript is not in the repository: docs/meetings/week3/week3.txt is the September 18 handover call.
#20 Sanity check the four findings the whole plan rests on Closed (September 29) Sprint 1 discovery. The last comment says that no result is recorded for the four claims.
#23 Get Frank to confirm priorities before we commit to the MoSCoW Closed (September 29) Client question. The last comment says that the MoSCoW order is not confirmed, so the MoSCoW stays provisional.
#252 Close the Sprint 2 rubric review gaps Closed Tracks the fix PRs into sprint-2 from the Sprint 2 rubric review. They change no story status.
#263 Merge the Sprint 2 PRs through sprint-2 and close out the sprint Closed Sprint 2 rubric follow-up.
#265 Give every open TA feedback row a plan or a reason Closed. Done by PR #277. Sprint 2 rubric follow-up.
#266 Re-estimate velocity per sprint and fix the planning mismatches Closed. Done by PR #277. Sprint 2 rubric follow-up.
#267 Remove leftover files, placeholder config and debug logs Closed. Done by PR #278. Sprint 2 rubric follow-up.
#268 Move the PDF-only queries out of the use server file and page all-reports Closed. Done by PR #279. Sprint 2 rubric follow-up.
#269 Run the Cypress specs locally and add E2E specs for 2.0.2 and 7.0.8 Closed. Done by PR #282. Sprint 2 rubric follow-up.
#270 Fix the wrong traceability matrix rows and add missing failure tests Closed. Done by PR #281. Sprint 2 rubric follow-up.
#272 Test the database access rules against the local Supabase Closed. Done by PR #282. Sprint 2 rubric follow-up.
#273 Stop the form editor reporting saved when option writes fail Closed. Done by PR #280. Sprint 2 rubric follow-up.
#274 Add E2E specs for 2.0.3 and 2.0.6 and a 2.0.3 AT3 failure test Closed. Done by PR #282. Sprint 2 rubric follow-up.

Sprint 2 task details

Each task is done when its PR is merged on main and the merged work covers the listed acceptance tests (AT) of its story. The acceptance tests are in User Stories. The test of each AT is in the Traceability Matrix.

Setup and foundations (due October 4 to 5)

  • Set up development, release, and feature branches. Assignee: Gamma (Zanab, Chris, Jayden). Make the branch model for the team: a development branch, a release branch, and feature branches from development. Add the branch rules on GitHub and write the model in Contributing. Done when a feature PR can merge into development and development can merge into the release branch. Result: PR #125 kept main as the development branch and added release. From Sprint 3, a sprint-N branch sits between the feature branches and main (see Sprint process).
  • Improve authentication checks for admin routes. Assignee: Beta (Abhinav, Alissa). Make sure that each admin page and admin server action checks on the server that the caller is an Admin. Done when a Steward who calls an admin route directly gets a refusal. This supports 2.0.2 AT4, 2.0.5 AT2, 3.0.2 AT4, 7.0.5 AT2, 7.0.6 AT3, 7.0.7 AT4 and 7.0.8 AT4.
  • Investigate and fix Invalid Identifier Supabase error. Assignee: Alpha (Saumya, Aaron). Find the cause of the error, fix it, and write the cause in the PR. Done when the error does not occur again.
  • Update db names to not include "W26" as prefix. Assignee: Alpha (Saumya, Aaron). Rename the database objects with a migration, and change each query that uses the old names. Done when the app works with the new names and no code uses the "W26" names.
  • Create user model that supports profiles, steward assignments, and gamified stats. Assignee: Alpha (Saumya, Aaron). Design the user data: name, email, skills, focus areas, contact info, inspection count, the sites that the user stewards, and fields for later activity points. Done when the model is reviewed by the team, because 1.0.1, 1.0.2 and 3.0.2 use it.
  • Migrate user model. Assignee: Alpha (Saumya, Aaron). Write the migration for the new user model and move the data of the current users. Done when all current users have a profile record and no data is lost.

Profiles (US 1.0.1, 1.0.2, 3.0.2)

  • Profile page (US 1.0.1). Assignee: Alpha (Saumya, Aaron). Show name, skills, focus area, contact info and inspection count. Open it from the main menu and from an inspection on a site page, with a way back. Done when 1.0.1 AT1 to AT5 pass.
  • Edit profile/user info page and functionality (US 1.0.2). Assignee: Alpha (Saumya, Aaron). A user edits only their own profile. Name and email are required. Skills and focus areas can be added. Done when 1.0.2 AT1 to AT6 pass, including the server refusal for another user's profile.
  • Add Steward to site page and link to their profile (US 3.0.2). Assignee: Alpha (Saumya, Aaron). An Admin searches for a steward and assigns or replaces the steward of a site. The site page and the steward's profile both show the assignment. Done when 3.0.2 AT1 to AT4 pass.

Sites (US 2.0.2, 2.0.3, 2.0.4, 2.0.5, 2.0.10)

  • Add new site page and functionality (US 2.0.2). Assignee: Gamma (Zanab, Chris, Jayden). An Admin makes a site, selects its boundary and gets a warning for a possible duplicate name. Required fields are checked. Done when 2.0.2 AT1 to AT6 pass.
  • Edit existing site page fields (US 2.0.5). Assignee: Gamma (Zanab, Chris, Jayden). An Admin enters edit mode, sees which fields are shown or hidden, and saves. Other users cannot enter edit mode. Done when 2.0.5 AT1 to AT4 pass.
  • Delete site button and confirmation (US 2.0.4). Assignee: Gamma (Zanab, Chris, Jayden). The Admin confirms the delete and sees how many inspections and images the delete affects. The site is archived first, and an Admin can restore it or delete it for good from the archive. Deleting for good removes the site and its steward link. Its reports, answers and photos stay in the database, detached from the site (site_id set to null) (PR #160). Done when 2.0.4 AT1 to AT4 pass.
  • Deactivate/Activate button and confirmation (US 2.0.3). Assignee: Beta (Abhinav, Alissa). An inactive site is not in site pickers or search, and its inspections can still be viewed. New sites are active. Done when 2.0.3 AT1 to AT5 pass.
  • Add links to site page (US 2.0.10). Assignee: Gamma (Zanab, Chris, Jayden). Show short links to the SAPAA website and iNaturalist that open in a new window. Done when 2.0.10 AT1 to AT3 pass.

Map (US 2.0.6)

  • Set up map. Assignee: Beta (Abhinav, Alissa). Add the map view to the web app. Done when the map loads for a signed-in user.
  • Add sites to the map. Assignee: Beta (Abhinav, Alissa). Show all active sites on the map. Done when each active site with a location is shown.
  • Add Search and Filtering on Map view. Assignee: Beta (Abhinav, Alissa). Filter sites by county, clear the filter, and search by name to centre the map on a site. Done when 2.0.6 AT1 to AT3 pass.

Site inspection reports (US 4.0.6, 7.0.1, 7.0.5, 7.0.6, 7.0.7, 7.0.8)

  • Change Photo Identifier field on SIR to not required (US 4.0.6). Assignee: Beta (Abhinav, Alissa). Remove the required rule and the "required" note. Done when 4.0.6 AT1 and AT2 pass.
  • Fix site inspection page resetting current page when app is exited temporarily (US 4.0.6). Assignee: Beta (Abhinav, Alissa). Keep the current page of the form when the user leaves the app and comes back. Done when the user returns to the same page with their answers.
  • Add a delete option on images (US 7.0.5). Assignee: Beta (Abhinav, Alissa). An Admin deletes an image, and the file is removed from S3. Other users see no delete control and the server refuses them. Done when 7.0.5 AT1 to AT5 pass.
  • Increase export limit to over 50 (US 7.0.6). Assignee: Gamma (Zanab, Chris, Jayden). Find the cause of the limit of 50 and remove it. Only Admins can export in bulk. Done when 7.0.6 AT1 to AT4 pass.
  • Screen to select hidden fields on SIR before export (US 7.0.7). Assignee: Beta (Abhinav, Alissa). An Admin selects fields to leave out of the export. The stored answers do not change. Done when 7.0.7 AT1 to AT5 pass.
  • Grant Steward permission to export PDFs (US 7.0.1). Assignee: Gamma (Zanab, Chris, Jayden). A Steward exports a PDF of their own SIR only. Done when 7.0.1 AT1 to AT3 pass.
  • Delete site inspection report button and confirmation (US 7.0.8). Assignee: Gamma (Zanab, Chris, Jayden). An Admin confirms, then the SIR and its images are removed from the site and report lists. Stewards are refused. Done when 7.0.8 AT1 to AT5 pass.

Accounts (US 5.0.4)

  • Fix logging out functionality outside the home page (US 5.0.4). Assignee: Alpha (Saumya, Aaron). Put sign-out on every page. After sign-out, the Back button and a new visit show the sign-in page. Done when 5.0.4 AT1 to AT3 pass.

Review and release

  • Open a PR for each task and request 2 reviews (everyone, October 10).
  • Code freeze (everyone, October 11). All Sprint 2 PRs are reviewed and merged. Work that is not merged is not assumed to carry over. The Product Owner places it at the October 14 planning.
  • Write the release notes and make the Sprint 2 release on GitHub (October 12). Assignee: Gamma (Zanab, Chris, Jayden). The release lists the finished stories and tasks. The deadline is October 13 at 20:00.
  • Sprint 2 demo, review and retrospective (everyone, October 14 lab). The Sprint 2 peer-review form is due October 14 at 23:59.

Sprint 3

Due: October 27, 2026, 20:00 (GitHub release). Code freeze October 25.

User stories

User Story Story points Issue or PR
US 1.0.3 - Show history of Site Inspections on a Steward's Profile 2 #169
US 1.0.4 - Aggregate User Activity and Contributions on a user's profile 2 #170
US 1.0.6 - Select and Edit Skills and Focus Areas 2 PR #308
US 2.0.1 - View Sites and Past Visits on an Interactive Map 8 #171
US 2.0.8 - View a Site's Details From the Map 3 #172
US 2.0.9 - Upload a GPX Track of a Site Visit 5 #173
US 2.0.12 - Score a Site for To-Visit Priority 8 PR #307
US 2.0.13 - Flag Site Points That Are a Year Old 3 PR #307
US 2.0.14 - Color Map Sites by Type 2 PR #313
US 3.0.3 - Export all digital files from SIR-SAPAA 8 PR #309
US 4.0.2 - Offline and Online Map Layers 13 #175
US 4.0.4 - Edit My Previous Inspections 5 #176
US 5.0.2 - Reset a Forgotten Password 2 #179
US 6.0.1 - Store Each Site's Geometry From the Shared Source 5 #180

Committed: 68 points. Re-estimate: 42 points (see Velocity re-estimate).

The sprint starts on October 14, after the Sprint 2 demo, review and retrospective. The planned code freeze was October 25, two days before the deadline. The freeze was missed; release checks record the remaining checks and approvals. Red makes the release on October 26. October 27 is spare time before the 20:00 deadline. Tasks are assigned to teams, not to people. Each team divides its tasks between its members. No Sprint 2 work carried over to this sprint.

The issues are in the Sprint 3 milestone: the original stories were #169 to #180 and the original tasks were #181 to #218. US 2.0.11 (#174), US 4.0.5 (#177) and US 4.0.7 (#178) are excluded from the current plan. Their task issues are #186, #197, #200, #202, #205, #211 and #212. The lists below show the remaining work. GitHub issue states are not changed by this document update.

The milestone also has four issues that are not story tasks:

Issue Title State
#251 Report read actions in queries.ts don't check the caller Closed. Fixed by PR #259, on main since #284. See Issues Backlog.
#264 Minute the Oct 14 lab, Sprint 2 retro and Sprint 3 planning Open
#271 Use one shared admin check and one S3 client Closed by PR #311. The export follow-up PR #318 also reuses the shared S3 client.
#275 Make S3 enforce the photo upload size and type limits Closed by PR #291.

Teams: Red (Saumya, Chris), Blue (Aaron, Zanab, Abhinav), Green (Alissa, Jayden). See Sprint 3 teams.

Scrum roles: Scrum Master Jayden, Product Owner Aaron. See Scrum roles.

Open questions before pointing

This step follows the TA's advice of September 30: the ambiguity of a story must not change its points, and a story is not complete until its details are clear. Owner: Aaron (Sprint 3 Product Owner).

  1. At Sprint 3 planning (October 14), each team adds an "Open questions" list to the issue of each of its Sprint 3 stories (#169 to #180). An empty list says "None".
  2. Aaron takes the questions for Frank to the October 16 client meeting and writes each answer in the issue.
  3. The points of a story do not change because of its open questions. If an answer changes the scope of a story, the team re-points it at the next planning and records why.
  4. From Sprint 4, a story is pointed only after its "Open questions" list is answered or says "None".

Tasks

Task Related US Assignee Due Issue
Link each site to its boundary from the Alberta government KML and store a centre point (migration) US 6.0.1 Blue (Aaron, Zanab, Abhinav) Oct 16th #181
Write the Sprint 3 test plan Dev Task Blue (Aaron, Zanab, Abhinav) Oct 16th #182
Review the schema of the site geometry columns, the GPX track table Dev Task Green (Alissa, Jayden) Oct 16th #183
Show all active sites with their boundaries on a map page for signed-in users US 2.0.1 Red (Saumya, Chris) Oct 17th #184
Create the GPX track table and file storage with access rules (migration) US 2.0.9 Red (Saumya, Chris) Oct 17th #185
Link each inspection in the profile history to its SIR US 1.0.3 Green (Alissa, Jayden) Oct 17th #187
Add "Forgot password" to the sign-in page and send a verification email US 5.0.2 Green (Alissa, Jayden) Oct 17th #188
Choose the tile source and the offline tile cache US 4.0.2 Red (Saumya, Chris) Oct 18th #189
Match sites in the KML import and list unmatched sites for an Admin US 6.0.1 Blue (Aaron, Zanab, Abhinav) Oct 18th #190
Add a "View on map" link to the site page and highlight only the selected site US 2.0.1 Red (Saumya, Chris) Oct 19th #191
GPX upload server action: check the extension, the GPX format, the track points and the size US 2.0.9 Red (Saumya, Chris) Oct 19th #192
Cache geocoding results and stay under the OpenCage daily limit, with tests for 6.0.1 US 6.0.1 Blue (Aaron, Zanab, Abhinav) Oct 19th #193
Open a past SIR in edit mode, and check on the server that only its author can edit it US 4.0.4 Blue (Aaron, Zanab, Abhinav) Oct 19th #194
Show activity aggregates on the profile and update them on a new SIR, with tests for 1.0.4 US 1.0.4 Green (Alissa, Jayden) Oct 19th #195
Add a CI check that fails when a diagram SVG does not match its Mermaid source Dev Task Red (Saumya, Chris) Oct 20th #196
Hide the fields that a steward chose to hide in their past SIRs, with tests for 1.0.3 US 1.0.3 Green (Alissa, Jayden) Oct 20th #198
Verify a code, then set the new password, with tests for 5.0.2 US 5.0.2 Green (Alissa, Jayden) Oct 20th #199
GPX upload control on the site page, with tests for 2.0.9 US 2.0.9 Red (Saumya, Chris) Oct 21st #201
Open a site detail view when a site is selected on the map US 2.0.8 Blue (Aaron, Zanab, Abhinav) Oct 21st #203
Block an edit that clears a required answer and list the missing questions US 4.0.4 Blue (Aaron, Zanab, Abhinav) Oct 21st #204
Draw the uploaded GPX tracks on the map, with tests for 2.0.1 US 2.0.1 Red (Saumya, Chris) Oct 22nd #206
Download a map area for offline use and show its download status US 4.0.2 Red (Saumya, Chris) Oct 22nd #207
"View SIRs" link from the site detail view, with tests for 2.0.8 US 2.0.8 Blue (Aaron, Zanab, Abhinav) Oct 22nd #208
Show the downloaded tiles offline and mark the missing tiles outside the downloaded area US 4.0.2 Red (Saumya, Chris) Oct 23rd #209
Show saved edits everywhere the report is rendered, with tests for 4.0.4 US 4.0.4 Blue (Aaron, Zanab, Abhinav) Oct 23rd #210
Use live tiles when online, with tests for offline and online mode US 4.0.2 Red (Saumya, Chris) Oct 24th #213
Update the traceability matrix for the Sprint 3 stories Dev Task Blue (Aaron, Zanab, Abhinav) Oct 24th #214
Add the three priority scores and their saved date to a site, and calculate the to-visit priority on the server (migration) US 2.0.12 Red (Saumya, Chris) Oct 25th PR #307
Admin score form and the to-visit priority on the site page. The server refuses a Steward's change. Tests for 2.0.12 US 2.0.12 Red (Saumya, Chris) Oct 25th PR #307
Show a reminder to an Admin when the points were saved more than a year ago, with tests for 2.0.13 US 2.0.13 Red (Saumya, Chris) Oct 25th PR #307
Export job that puts all stored images and files in one ZIP file US 3.0.3 Red (Saumya, Chris) Oct 25th PR #309
Admin control to start the export and download the ZIP file, with tests for 3.0.3 US 3.0.3 Red (Saumya, Chris) Oct 25th PR #309
Skill and focus area dropdowns with an "Other" option and suggestions on the profile edit form, with tests for 1.0.6 US 1.0.6 Red (Saumya, Chris) Oct 25th PR #308
Open a PR for each task and request 2 reviews All US Everyone Oct 24th #215
Code freeze: all Sprint 3 PRs reviewed and merged All US Everyone Oct 25th #216
Write the release notes and make the Sprint 3 release on GitHub Release Red (Saumya, Chris) Oct 26th #217
Sprint 3 demo, review and retrospective All US Everyone Oct 28th #218

Sprint 3 task details

Each task is done when its PR is merged and the listed acceptance tests (AT) of its story pass. The acceptance tests are in User Stories.

Dependencies. The work that other tasks build on is due first:

  • 6.0.1 (site boundary and centre point, October 16) comes before the map page (2.0.1), the boundaries on the map.
  • The map page of 2.0.1 (October 17) comes before the site detail view (2.0.8), the GPX tracks on the map (2.0.1 AT2) and the offline layers (4.0.2). It builds on the base map of PR #159.
  • The GPX track table (2.0.9, October 17) comes before the GPX upload and the tracks on the map.
  • Green reviews the schema of the new columns and tables (October 16) before their migrations merge. The review also records which SIR fields a steward can hide (1.0.3 AT3).

Red (Saumya, Chris): map, GPX tracks, offline layers, the five stories moved from Sprint 4 and the release

  • Show all active sites with their boundaries on a map page for signed-in users (US 2.0.1). Use MapLibre GL and the Protomaps basemap from PR #159. Build on the map in webapp/components/map/SiteMap.tsx, which already draws the protected area boundaries (PR #161, PR #167), and use the geometry from 6.0.1. Done when 2.0.1 AT1 passes.
  • Add a "View on map" link to the site page and highlight only the selected site (US 2.0.1). Done when 2.0.1 AT3 and AT4 pass.
  • Draw the uploaded GPX tracks on the map (US 2.0.1). Draw a track as a line in a different style from the site boundary. Done when 2.0.1 AT1 to AT4 pass.
  • Create the GPX track table and file storage with access rules (US 2.0.9). Link each track to a site and to the user who uploaded it. Done when the migration runs on a clean local database and Green has reviewed the schema.
  • GPX upload server action (US 2.0.9). Refuse a file without the .gpx extension, a file that is not valid GPX or has no track points, and a file above the stated maximum size. Save nothing when a file is refused. Accept several files in one upload and check each file on its own. Frank asked for bulk upload at the October 9 meeting (docs/meetings/week6/2026_10_09_meeting_frank.txt). Done when 2.0.9 AT2, AT3, AT5 and AT6 pass.
  • GPX upload control on the site page (US 2.0.9). Let the user choose one or several files. Done when 2.0.9 AT1 to AT6 pass, including the read-back of the same track points (AT4).
  • Choose the tile source and the offline tile cache (US 4.0.2). The tile source is decided: PR #159 uses Protomaps with MapLibre GL. Choose the offline cache for those tiles and write the decision and its limits in the PR. Done when the team agrees on the approach.
  • Download a map area for offline use and show its download status (US 4.0.2). Done when 4.0.2 AT1 passes.
  • Show the downloaded tiles offline and mark the missing tiles (US 4.0.2). Done when 4.0.2 AT2 and AT3 pass.
  • Use live tiles when online (US 4.0.2). Done when 4.0.2 AT1 to AT4 pass.
  • Add the three priority scores and their saved date to a site, and calculate the to-visit priority on the server (US 2.0.12). Migration. Green reviews the schema. Done when 2.0.12 AT1 to AT3 pass.
  • Admin score form and the to-visit priority on the site page (US 2.0.12). An Admin saves the scores. A Steward sees the priority and the scores, and the server refuses a Steward's change. Done when 2.0.12 AT1 to AT5 pass.
  • Show a reminder to an Admin when the points are a year old (US 2.0.13). Uses the saved date of 2.0.12. Done when 2.0.13 AT1 to AT4 pass.
  • Export job that puts all stored images and files in one ZIP file (US 3.0.3). Runs as a background job, see the sequence diagram in Software Design. Done when 3.0.3 AT1 and AT2 pass.
  • Admin control to start the export and download the ZIP file (US 3.0.3). Admin only. Done when 3.0.3 AT1 and AT2 pass.
  • Skill and focus area dropdowns on the profile edit form (US 1.0.6). Include an "Other" option and suggest similar existing values. Done when 1.0.6 AT1 to AT3 pass.
  • Add a CI check that fails when a diagram SVG does not match its Mermaid source (dev task). The check runs on PRs that change docs/assets/*.mmd or docs/images/*.svg. Done when a PR with an out-of-date SVG fails the check.

Blue (Aaron, Zanab, Abhinav): site geometry, site details, boundary colors and SIR edits

  • Link each site to its boundary and store a centre point (US 6.0.1). This continues the KML parser and import from PR #137 and PR #152, and the site-to-area link that PR #167 added. That link is empty until an Admin sets it. This task fills it from the KML for the existing sites. Done when 6.0.1 AT1 and AT2 pass and Green has reviewed the schema.
  • Match sites in the KML import and list unmatched sites for an Admin (US 6.0.1). Done when 6.0.1 AT3 passes.
  • Cache geocoding results and stay under the OpenCage daily limit (US 6.0.1). Done when 6.0.1 AT1 to AT4 pass.
  • Open a site detail view when a site is selected on the map (US 2.0.8). Use the same data as the site page. This task needs the base map of 2.0.1. Done when 2.0.8 AT1 and AT2 pass.
  • "View SIRs" link from the site detail view (US 2.0.8). Done when 2.0.8 AT1 to AT3 pass.

  • Open a past SIR in edit mode, and check on the server that only its author can edit it (US 4.0.4). Done when 4.0.4 AT1 and AT2 pass.

  • Block an edit that clears a required answer (US 4.0.4). List the missing questions. Done when 4.0.4 AT3 passes.
  • Show saved edits everywhere the report is rendered (US 4.0.4). This includes the site page, the profile history and the PDF export. Done when 4.0.4 AT1 to AT4 pass.
  • Write the Sprint 3 test plan (dev task). Name the test type (unit, integration or E2E) for each acceptance test of the Sprint 3 stories. Done when the team has reviewed the plan.
  • Update the traceability matrix for the Sprint 3 stories (dev task). Link each acceptance test to its test and its PR. Done when each Sprint 3 acceptance test has a row.

Green (Alissa, Jayden): profiles, password reset and the schema review

  • Link each inspection in the profile history to its SIR (US 1.0.3). The history list (site and date) is already on the profile from PR #138. Done when 1.0.3 AT1 and AT2 pass.
  • Hide the fields that a steward chose to hide in their past SIRs (US 1.0.3). Done when 1.0.3 AT1 to AT3 pass.
  • Show activity aggregates on the profile and update them on a new SIR (US 1.0.4). The profile already shows the SIR count from PR #138. Add the reported activities. Done when 1.0.4 AT1 and AT2 pass.
  • Add "Forgot password" to the sign-in page and send a verification email (US 5.0.2). Done when 5.0.2 AT1 passes.
  • Verify a code, then set the new password (US 5.0.2). No Admin step is needed. Done when 5.0.2 AT1 to AT4 pass.

Review and release

  • Open a PR for each task and request 2 reviews (everyone, October 24).
  • Code freeze (everyone, October 25). All Sprint 3 PRs are reviewed and merged.
  • Write the release notes and make the Sprint 3 release on GitHub (October 26). Assignee: Red (Saumya, Chris). The release lists the finished stories and tasks. The deadline is October 27 at 20:00.
  • Sprint 3 demo, review and retrospective (everyone, October 28 lab).

Sprint 4

Due: November 17, 2026, 20:00 (GitHub release). Code freeze November 15.

User stories

User Story Story points
US 1.0.5 - Earn Points for Inspection Activity 5
US 5.0.5 - Request Access During Email Sign-Up 8
US 5.0.6 - Complete an Access Request With Google or Microsoft 5
US 5.0.7 - Review and Decide Access Requests 8
US 5.0.8 - Manage Access Terms 5
US 5.0.9 - View My Access-Request Status 3
US 7.0.3 - See All Inspections in One View 5

Committed: 39 points. Re-estimate: 61 points (see Re-estimate after Sprint 3).

Sprint 4 is left open on purpose. The team waits for Frank's other versions of the requirements and plans the sprint from what he says, so the story issues are not written yet. One Sprint 4 issue exists (#306, for 5.0.8). The five access-request stories are Frank's new version 3.0 request. They use the capacity that was reserved for new client requests. The sprint is 20 points below the capacity estimate of 59, which leaves room for the Sprint 3 gaps.

The October 16 requests are US 1.0.6, US 2.0.14 and US 3.0.4. Owner: Team. US 2.0.14 is in Sprint 3, assigned to Team Blue (Aaron, Zanab, Abhinav). US 1.0.6 and US 3.0.4 moved from Sprint 4 to Sprint 3 on October 24, with 5 points in total. US 3.0.4 was removed on October 26. US 1.0.6 remains assigned to Red. All three have Should Have priority.

Tasks

Issue Work Points Assignee State
#306 US 5.0.8: move the SIR-SAPAA terms and conditions into the access-request page part of 5 Chris, Abhinav Open
#329 US 2.0.1 AT1: draw the sites that have no boundary - Saumya Open
#330 US 2.0.14: add a map legend for the site-type colors - Saumya Open
#331 US 2.0.8 AT3: align the popup link with the AT - To confirm Open
#332 US 1.0.3 AT1 and US 4.0.4 AT4: cover the partly tested ATs (1.0.3 AT1 has been covered since October 27, so only 4.0.4 AT4 is left) - To confirm Open
#333 US 2.0.12: ask Frank to confirm the priority formula - Zanab (Product Owner) Open
#334 New story from Frank (October 23): last 5 GPX files of a site, tied to a visit - Zanab (Product Owner) Open
#335 Remove the leftover empty.md and mock_data.sqlite - To confirm Open

The seven issues #329 to #335 were written on October 26 from the Sprint 3 review. Assignees marked "To confirm" are set at Sprint 4 planning (October 28).

Sprint 3 gaps that carry into Sprint 4. These are ATs of Sprint 3 stories, not new stories, and they have no new points: 2.0.1 AT1 (sites without a boundary are not drawn) and 4.0.4 AT4 (every view after an edit is not rechecked). Proposed story, not yet pointed. On October 23 Frank asked for a new story (action 1 of Meeting #11): show only the last 5 GPX files of a site by default, with older ones on request, and tie each GPX upload to a site visit. It has no number, points or priority yet, and it is not in the totals above. It changes US 2.0.9 and US 2.0.1. Frank and the Sprint 4 Product Owner (Zanab) decide the points and the priority when Sprint 4 is planned.

The issues for the Sprint 4 stories are written when Frank's other versions are in and the Product Owner has confirmed the scope and the assignees. Each issue then gets the ATs from User Stories, labels, the Sprint 4 milestone and an assignee.

Sprint 5

Due: December 1, 2026, 20:00 (GitHub release). Code freeze November 29.

Sprint 5 is kept free on purpose. The client said that more work can come. The sprint is also for final polish, deployment and fixes for the client field test in early December.

User stories

No stories planned yet. New client requests go here.

Committed: 0 points. Re-estimate: 57 points (see Velocity re-estimate).

No stories are committed yet. About 30 points are for new client requests and carry-over from Sprint 4. The rest is for deployment, final polish and field-test fixes.

Tasks

Tasks are planned at the start of the sprint.


Archive: Winter 2026 project plan (previous team)

The plan below belongs to the Winter 2026 team (Jason Liang, Raiyana Rahman, Vishal Sivakumar, Harveer Deol, Braden Woods, Akib Zaman Choudhury, Zoe Prefontaine). It is kept as the delivery record for the code this project inherited. It is not the Fall 2026 plan and the names, dates and story numbers in it refer to their work, not ours.

Their Sprint 1 roles were Scrum Master Jason Liang, Product Owners Harveer Deol and Raiyana Rahman. Their story map is at images/W26-SAPAA-Storymap.png and their MURAL board is on a workspace we do not have access to.

Sprint 2

Due: February 15, 2026

User stories

User Story Story points
US 1.0.1 – Access Site Inspection Form on Web Application 3
US 1.0.2 – Add Personal Information to Site Inspection Form [Q11-Q14 + Q16 + Q24 - Section : WhoRYou] 1
US 1.0.3 - Liability Check [Q2 - Section : General] 1
US 1.0.4 - Have access to the Terms and Conditions of Inputting Information [Q3 - Section: The Fine Print Up Front] 1
US 1.0.5 - Add Details Regarding the Overview of my Visit [Q21, Q22, Q23, Q25 - Section : WhereRYou] 1
US 1.0.6 - Rank the Health of the Site [Q31-33 Section : Impression] 1
US 1.0.7 - Add Details Regarding How the Trip Went [Q41 - 43 - Section : How Visit] 1
US 1.0.8 - Address What Amenities are in the Site [Q51 : Section - Be There] 1
US 1.0.9 - Designation as a Protected Site [Q55 - Section : Be There] 1
US 1.0.10 - Indicate submissions to iNaturalist [Q53 - Section : Be There, Q68] 1
US 1.0.11 - Address details of Landscape changes [Q54 - Section : Be There] 2
US 1.0.12 - Address any Biological Observations that are in the Site [Q52 - Section : Be There, Q68] 1
US 1.0.13 - Address Any Human Disturbances - Section 8 [Q61 - Q66 - Section : Not There] 1
US 1.0.14 - Add Other Comments [Q56, Q67, Q74, Q82] 2
US 1.0.15 - Inform SAPAA of Any Restorative Work that Needs to be Done / Was Done [Q71, Q72 - Section : 2B Done] 2
US 1.0.23 - Non-Public Information [Q73, Q83] 2
US 1.0.26 - Persist Site Inspection Form Draft 5
US 1.0.27 - Enforce Required Questions on Site Inspection Form 3
US 1.0.28 - Autofill Applicable Form Questions 3
TASK 1.0.29 - Refactor the Database Schema and Produce an Updated ER Diagram N/A

Sprint Velocity: 33

Tasks

Task Related US Assignee Due
Build the Site Inspection Form entry point US 1.0.1 Vishal, Jason, Raiyana Feb 7th
Refactor the Database Schema TASK 1.0.29 Raiyana, Zoe Feb 7th
Understand previous team's implementation to repurpose for our schema US 1.0.1 Vishal, Harveer, Jason, Braden Feb 7th
Produce an Updated ER Diagram TASK 1.0.29 Raiyana Feb 7th
Add the liability check and access gate US 1.0.3 Harveer Feb 8th
Add the Terms & Conditions acceptance flow US 6B.01 Harveer Feb 8th
Create the personal information section US 1.0.2 Braden Feb 11th
Create the visit overview and site selection section US 1.0.5 Vishal Feb 11th
Add the non‑public information fields US 1.0.23 Harveer Feb 11th
Develop the site health and impression section US 1.0.6 Zoe Feb 11th
Develop the trip details and visit reasoning section US 1.0.7 Braden Feb 11th
Add the landscape change reporting fields US 1.0.11 Braden Feb 11th
Add the biological observations section US 1.0.12 Jason Feb 11th
Add the human disturbances reporting section US 1.0.13 Zoe Feb 11th
Create the amenities and ease‑of‑use section US 1.0.8 Akib Feb 11th
Create the protected site designation section US 1.0.9 Akib Feb 11th
Add the iNaturalist submission indicator US 1.0.10 Akib Feb 11th
Add the additional comments and free‑text section US 1.0.14 Vishal, Raiyana Feb 11th
Add the restoration actions and stewardship section US 1.0.15 Zoe Feb 12th
Persist Site Inspection Form Draft US 1.0.26 Jason, Raiyana Feb 12th
Enforce Required Questions on Site Inspection Form US 1.0.27 Jason, Akib Feb 12th
Autofill Applicable Form Questions US 1.0.28 Zoe Feb 12th
Assemble all sections into a unified form schema All US Everyone Feb 14th
Finalize the submission flow and validation logic All US Everyone Feb 14th
Write acceptance tests All US Everyone Feb 14th
Update documentation Documentation Everyone Feb 14th

Sprint 3

Due: March 8, 2026

User stories

User Story Story points
US 1.0.16 – Add Any Photography Captured During Visit 5
US 1.0.17 – (Admin) Add Questions Site Inspections Form 3
US 1.0.18 – Adding Image Identifier 2
US 1.0.19 - Admin Viewing Images and Metadata 2
US 1.0.22 – (User) Edit My Site Inspections Form 5
US 1.0.24 – Modify my Site Inspections Form Questions 8
US 1.0.25 – Hide a Site Inspections Form Questions 3
US 2.0.1 – Manage the uploading and storing of site inspection images 8
US 2.0.2 – Image Metadata 2
US 2.0.3 – Gallery View 3
TASK 2.0.6 - Refactor Report Rendering to Use Updated Database Schema N/A

Sprint Velocity: 41

Tasks

Task Related US Assignee Due
Setup AWS account with client All US Harveer Feb 20th
Setup developer email for vercel with client All US Harveer Feb 20th
Add any photography captured during visit US 1.0.16 Raiyana Feb 25th
Allow admin to add Questions Site Inspections Form US 1.0.17 Braden Feb 27th
Adding Image Identifier to the inspection form US 1.0.18 Raiyana, Zoe Feb 27th
Add a dashboard for admin to view images and metadata US 1.0.19 Raiyana Mar 3rd
Add the ability to edit previous site inspections forms for users US 1.0.22 Vishal Mar 3rd
Let admin modify the site inspections form questions US 1.0.24 Braden, Jason Mar 3rd
Add ability to hide site inspection form questions US 1.0.25 Braden, Jason Mar 5th
Manage the uploading and storing of site inspection images onto S3 US 2.0.1 Raiyana, Harveer Mar 5th
Image Metadata US 2.0.2 Raiyana, Akib Mar 5th
Gallery View US 2.0.3 Raiyana, Akib Mar 5th
Refactor Report Rendering to Use Updated Database Schema TASK 2.0.6 Vishal Mar 7th
Finalize the submission flow and validation logic All US Everyone Mar 7th
Write acceptance tests All US Everyone Mar 7th
Update documentation Documentation Everyone Mar 8th

Sprint 4

Due: March 22, 2026

User stories

User Story Story points
US 1.0.30 – Rich Text Formatting for Form Description Fields 3
US 2.0.7 – Admin Management of Media Files 13
US 2.0.8 – User Upload of Standalone Site Images 8
US 4.0.1 – PDF Generation of SIR's 8
US 4.0.3 – Update Site Profile of a Particular Site 3
US 4.0.4 – Disable Site Profile of a Particular Site 3
US 5.0.1 - Admin Approval of Users 5

Sprint Velocity: 43

Tasks

Task Related US Assignee Due
Rich Text Editor US 1.0.30 Akib, Braden Mar 11th
Admin Management of Media Files US 2.0.7 Jason, Raiyana, Zoe Mar 12th
Enable user upload of standalone site images US 2.0.8 Raiyana, Vishal Mar 13th
PDF generation US 4.0.1 Braden, Vishal, Jason Mar 15th
Update existing site profiles US 4.0.3 Braden, Jason Mar 17th
Disable site profiles as needed US 4.0.4 Braden, Jason Mar 19th
Admin Approval of Users US 5.0.1 Harveer Mar 19th
Finalize Sprint 4 acceptance tests All US Everyone Mar 21st
Update documentation Documentation Everyone Mar 22nd

Sprint 5

Due: March 31, 2026

User stories

User Story Story points
US 1.0.20 - Admin Editing Image Metadata 3
US 2.0.4 - Offline Image Viewing 5
US 2.0.9 – Homescreen Gallery View 5
US 3.0.1 - Access the mobile version of the Site Inspection Form 5
US 3.0.2 - Offline Data Syncing 8
US 5.0.2 – Sign Out Feature 2
TASK 6.0.1 – Web Application Responsiveness N/A
TASK 6.0.2 – Front-End Error Handling & Validation N/A
TASK 6.0.3 – Inspection Fields Integration N/A

Sprint Velocity: 28

Tasks

Task Related US Assignee Due
Homescreen Gallery View US 2.0.9 Vishal Mar 25th
Web Application Responsiveness TASK 6.0.1 Raiyana Mar 26th
Sign out feature US 5.0.2 Harveer Mar 27th
Inspection Fields Integration TASK 6.0.3 Akib, Jason Mar 27th
Front-End Error Handling & Validation TASK 6.0.2 Akib Mar 28th
Deployment Instructions Documentation Harveer, Raiyana Mar 29th
Job Description Documentation Braden, Vishal Mar 29th
User manual Documentation Braden Mar 30th
Admin manual Documentation Braden, Jason Mar 30th
UI Consistency All US Everyone Mar 30th
Finalize Sprint 5 acceptance tests All US Everyone Mar 30th
Project Portal Upload Documentation Harveer Mar 29th
Finalize documentation Documentation Everyone Mar 31st

V3 production feedback release — October 31, 2026

Owner for this fix set: Tars, at the user's request. The independent code/security reviewer approved the implementation after the photo owner lazy-loading guard was corrected. Human acceptance remains with the SAPAA team. No new issue or pull request was opened.

Task Status Evidence
Default A–Z, quick sort, and Z–A in list and map Implemented; automated checks passed V3-01, V3-02, V3-03, V3-05 in the traceability matrix
Clear carried filters and center map filter dialogs Implemented; automated checks passed V3-06, V3-07
Admin corrections to incomplete historic reports Implemented; mocked checks V3-04; owner and approval guards retained
Keep saved report values and visit date Implemented; mocked checks V3-09; no edit autofill
Open content links separately Checked and email/phone URL handling corrected V3-08
Copy shared fields across a photo batch Implemented; mocked checks V3-10; explicit button, captions stay separate
Show missing required fields Implemented; mocked checks V3-11; text and invalid state
Edit photo fields as owner/admin Implemented; mocked checks V3-12; Delete remains admin-only
Restore photo loading against current production schema Deployed and real images read bfba34f9; removed nonexistent photo-table created_at projection
Deployment guide with verified database usernames and screenshots Written; documentation build checked Production guide

The release does not change production data as a test. In particular, the example Dussault Lake email correction in the client's note is a reproduction case. The implementation permits that correction; the release check does not change the saved report. Real uploads, imports, and field acceptance on physical devices remain team checks.

SAPAA Dev release pipeline — October 31, 2026

Owner: Tars, at the user's request. Design approved by the user: course prod, successful CI, SAPAA-Dev main, staged Vercel build, and manual Vercel promotion.

Task Status
Copy course main to SAPAA-Dev main Verified at f5843c5d; same commit, history retained
Deploy SAPAA-Dev main to stable Vercel app Ready deployment H8mg9EMYMCyTbf4XE9qoEfwpsbAZ with stable domain verified
Set Vercel manual release gate Saved and verified; branch main, automatic domain assignment disabled
Sync workflow and local success/failure tests Implemented; shell tests and actionlint passed
Restricted GitHub App and course Actions credentials Installed on the one deployment repository; App authentication and scope verified; encrypted secret and App ID saved; temporary key removed
Workflow review and merge PR #345 merged at 38cbeee6; independent review approved
Private source checkout and detailed screenshot guide PR #346 merged at 8bba6f08; source tests and actionlint passed
Release runner Hosted CI run 41249841693 blocked by account billing before tests. Owner selected runner CI on Cybera; PR #347 merged at 719470e3
Real prod-branch pipeline run Prod CI 41250170369 and automatic sync 41251999586 passed; SAPAA-Dev main equals 719470e3; Vercel build completed
New stable production promotion Verified in Brave: DoNvxUMvkCSk8XhUy6XUA6Zvykfu, Ready / Production Current, Source main at 719470e3, stable domain assigned
Read-only production checks Map tiles/pins, 270 sites A–Z, expand/global zoom, and real S3 photo pixels loaded

See the production guide for the release procedure. The first full CI → sync → Vercel build → manual promotion cycle was verified at 719470e3. Every later release needs its own source and domain checks.

Go-live email fixes — November 1, 2026

Owner: Tars, at the user's request. Issues were created before code changes. This is a review branch based on current main; it does not deploy or change production records. The older sprint-4 branch does not contain the current v2 interface.

Issue Task Status
#349 Keep the admin exception for incomplete history in the report API as well as the shared editor Implemented; local checks recorded in the PR
#350 Render links in report values and notes through the existing safe link component Implemented; local checks recorded in the PR
#351 Verify saved visit dates and blank historic dates remain unchanged Existing form fix verified; API regression coverage added
#352 Add a visible Users link for admins Implemented; local checks recorded in the PR
#353 Open the existing steward selector directly from site details Implemented; local checks recorded in the PR
#354 Add explicit report owner selection with server checks Implemented; local checks recorded in the PR

Human review and acceptance remain pending. Cypress is not run because repository rules prohibit it. No account email, steward assignment, or report owner was changed in production. Steward retirement and historical assignment rules remain future scope in #353.

Local validation: 2,070 Jest tests passed and 36 were skipped. TypeScript and lint on the changed files passed. The documentation build passed. An independent code and security review found no blockers. Its focus-return suggestion was fixed and has an interaction test.