Team Project Marking: Sprint 4
In this sprint, you will deliver ~85% of the requirements. The prototype should be functional and usable but may have a few rough edges.
Late release submission policy
Applies to all sprints.
If a sprint release is late for less than 24 hours: penalty of 5 marks.
If late for more than 24 hours: penalty at the instuctor's discretion, min. 10 marks.
Rubric
Deliverable | Marks |
---|---|
Revisions | 10 |
UX, UI design | 10 |
Codebase | 30 |
Testing | 15 |
Sprint planning | 10 |
Teamwork | 15 |
Addressing TA feedback | 10 |
Total | 100 |
Revisions, UX, UI design, Codebase, Testing, Teamwork, and Addressing TA feedback deliverables are similar to the ones in the previous sprint.
Sprint planning
- Storymap clearly represents the current state of the project
- Project plan is updated to reflect the current state of the project
- Velocity is re-estimated for Sprint 5
- Sprint 5 tasks are included in the project plan
- Detailed Github Issues for Sprint 5 correspond with the storymap and project plan, have relevant states, milestones, labels and assignees