Team Project Marking: Sprint 4

In this sprint, you will deliver ~85% of the requirements. The prototype should be functional and usable but may have a few rough edges.

Late release submission policy

Applies to all sprints.

If a sprint release is late for less than 24 hours: penalty of 5 marks.

If late for more than 24 hours: penalty at the instuctor's discretion, min. 10 marks.

Rubric

Deliverable Marks
Revisions & Addressing TA feedback 15
UX, UI design 10
Codebase 35
Testing 15
Sprint planning 10
Teamwork 15
Total 100

Revisions & Addressing TA feedback, UX, UI design, Codebase, Testing, and Teamwork deliverables are similar to the ones in the previous sprint.

Sprint planning

  • Storymap clearly represents the current state of the project
  • Project plan is updated to reflect the current state of the project
  • Velocity is re-estimated for Sprint 5
  • Sprint 5 tasks are included in the project plan
  • Detailed Github Issues for Sprint 5 correspond with the storymap and project plan, have relevant states, milestones, labels and assignees